The unit will start commercial operation within 54 months.
According to the statement, BHEL has secured an order under international competitive bidding, for setting up a 1x800 MW Ukai supercritical thermal power plant (Unit-7) on an Engineering, Procurement & Construction (EPC) basis, in Tapi district, Gujarat.
Notably, the proposed unit will be set up on the existing ash dyke area.
BHEL's scope of work in the project envisages design, engineering, manufacturing, supply, testing, and commissioning for the EPC package, along with all necessary electrical, civil, and structural works.
The scope also includes the supply of highly efficient emission control equipment.
Popular in Energy
Notably, the first thermal unit at Ukai was also installed by BHEL in 1976, marking decades of successful partnership.
As India's foremost power equipment manufacturer, with over 1,70,000 MW of utility power capacity installed across the country, BHEL continues to play a pivotal role in bolstering India's energy security and supporting the vision of self-reliance in the power sector.