10M Downloads

Today’s NewsQuick ReadsE-PaperStockRecosStream

RERA Impact: Builder asked to pay Rs 2.56 crore compensation and foreclose homebuyer’s housing loan due to 7-year delay in possession of flat

TIL Creatives
RERA Impact: Builder asked to pay Rs 2.56 crore compensation and foreclose homebuyer's housing loan

Story Outline

RERA said:
  • None of the reasons submitted by the builder has any force and legal validity to justify the delay in completion of the project and provide any exception from the application of Section 18 of the RERA Act, 2016.
  • The builder is directed to refund a sum of Rs 2.56 crore (2,56,47,520) towards refund with interest to the homebuyer as per the calculation submitted by the homebuyer, within 60 days from the date of this order, calculated from April 10, 2014 till November 2, 2024.
Who knew purchasing a home from a reputed builder under the pre-EMI scheme could turn into a nearly decade-long ordeal. This is the experience of a homebuyer who bought an apartment worth Rs 80 lakh in March 2014 by using his personal savings of Rs 15 lakh and securing a home loan for the remaining amount of Rs 65 lakh from a bank. This homebuyer signed a tripartite agreement with the bank and builder which said that all pre-EMIs would be reimbursed by the builder until the possession of the apartment is handed over, specifically by March 31, 2017.

ADVERTISEMENT
However, the builder neither delivered the apartment by March 31, 2017, nor reimbursed any of the pre-EMI amounts as per the agreement. The homebuyer had to pay all the pre-EMIs to the bank till June 2024. The bank continued to charge all the pre-EMIs to the homebuyer despite the builder abdicating its responsibility of reimbursing pre-EMIs and there was no visible sign of the apartment’s construction getting finished. Ultimately this homebuyer had to approach the Karnataka High Court in 2024 to obtain a restraining order against the bank, preventing it from initiating any sort of precipitative actions, including but not limited to civil or criminal proceedings to recover the outstanding loan amount.

While the high court did grant this appeal and issued the restraining order in June 2024, the homebuyer had to approach the Karnataka RERA tribunal to fight for an order mandating the builder to refund the money and foreclose the bank loan and give reimbursement for all the pre-EMIs paid. The Karnataka RERA, after analysing the case, applied Section 18 of the RERA Act, 2016, and ordered the builder to not only foreclose the home loan but also to pay Rs 2.56 crore to the homebuyer, including interest.


Read below to understand how this homebuyer won this case against the builder and obtained a restraining order against the bank. The legal analysis and reasoning applied in this case might help you in similar situations.

How did this case start?

According to the order of Karnataka RERA dated March 24, 2025, here’s a timeline of events:

  • March 29, 2014: The bank sanctioned a Rs 65 lakh (Rs 65,65,776) home loan and disbursed the amount to the builder in full.
  • April 24, 2014: The builder signed a sale agreement with the homebuyer. On this same date, the homebuyer paid Rs 15 lakh (15,56,872) from his savings, in addition to the home loan already paid by the bank earlier.
  • May 26, 2014: The builder, homebuyer, and the bank signed a tripartite agreement about the Rs 65 lakh home loan and its pre-EMI terms and conditions. The builder also signed a letter of undertaking on this same date agreeing to reimburse all the pre-EMIs of this loan till the date of expected possession of the apartment, i.e., March 31, 2017.
  • May 26, 2014, till January 18, 2017: The builder failed to reimburse any of the pre-EMI amounts, while the bank continued to charge the homebuyer these pre-EMI amounts, which he continued to pay.
  • January 18, 2017: The homebuyer cancelled the booking, and the builder acknowledged this cancellation on January 24, 2017.
  • January 24, 2017, till July 26, 2024: Neither the builder nor the bank discharged the homebuyer from repayment obligations for the home loan, as agreed under the letter of undertaking signed on May 26, 2014. Hence, the home loan EMI liabilities continued as if the booking had never been cancelled.
  • July 26, 2024: The Karnataka High Court passed a restraining order stopping the bank from initiating/continuing any civil or criminal proceedings against the homebuyer for recovery of the outstanding home loan amount.
  • November 2, 2024: The homebuyer files a case in Karnataka RERA tribunal against the builder.

ADVERTISEMENT

The builder’s lawyers said in Karnataka RERA that demonetisation, GST, and Covid-19 prevented him from completing the apartment’s construction for 8 years

As per the order of Karnataka RERA, the builder’s lawyers said: There is a delay in completing the project, and the builder could not hand over the apartment as per the agreed timeline. The reasons for the delay in completion of the project are:

  1. Legal and licensing issues
  2. Heavy and continuous rainfall and flooding in the project site
  3. Demonetisation
  4. Introduction of GST
  5. Restrictions imposed on working hours due to curb on sand mining, shortage of skilled labour, steel and other construction materials
  6. Covid-19 lockdown imposed by the government

Karnataka RERA says builder can’t say Covid-19 prevented him from completing the project when its possession deadline was March 2017

Karnataka RERA said:

ADVERTISEMENT
  • None of the reasons submitted by the builder have any force and legal validity to justify the delay in completion of the project and provide any exception from the application of Section 18 of the RERA Act, 2016.
  • Further, one of the contentions raised by the builder for the delay in completing the project is on account of Covid-19. As stated earlier, the delivery and completion of the project was March 31, 2017, and the actual Covid-19 pandemic started during the year 2020, and the builder cannot plead before the authority the Covid-19 pandemic as the reason for the delay in completing the project. There, the reason sought by the builder on account of Covid-19 for the delay in completing the project is not tenable, and the same is not agreed to by the authority.

Karnataka RERA judgement: Builder is ordered to pay Rs 2.56 crore in compensation for the delay and foreclose the home loan

The Karnataka RERA said:

  • The builder is directed to refund a sum of Rs 2.56 crore (Rs 2,56,47,520) towards the refund with interest to the complainant as per the calculation submitted by the homebuyer, within 60 days from the date of this order, calculated from April 10, 2014, till November 2, 2024. The interest due from November 3, 2024, up to the date of final payment will be calculated likewise and paid to the homebuyer.
  • The builder is directed to close the loan standing in the name of the homebuyer.
  • The homebuyer is at liberty to initiate action for recovery in accordance with law if the respondent fails to pay the amount as per the order.

ADVERTISEMENT
Karnataka RERA

Subrata Mukherjee, Partner, SNG & Partners, Advocates & Solicitors, says: “The homebuyer won the case due to the inordinate delay by the builder in handing over the apartment. The said delay was admitted by the builder and was not sufficiently explained. Further, the builder did not produce any documentary evidence to support the reasons for the delay. Hence, in terms of section 18 of the RERA Act, the homebuyer has the right to withdraw from the project and claim the return of the entire refund of the amount paid by the homebuyer to the builder along with interest payable.”

Karnataka RERA explains why it ordered the builder to pay Rs 2.56 crore to the homebuyer
The Karnataka RERA explains the reason for this judgement:
ADVERTISEMENT

Point 1: Delay in possession of the house violated Section 18 of the RERA Act

The grievance of the homebuyer is that their apartment was not completed within the promised possession date, i.e., March 31, 2017, and since they were given the option to withdraw from the purchase from the builder by signing a pre-EMI scheme document at the very conception of the purchase, the homebuyer chose to exercise this option to withdraw.

In view of the builder’s admission and acceptance of the homebuyer’s withdrawal and from all available records submitted before this RERA authority, there has been a delay in giving possession, and therefore, the complainant is entitled to the relief of a refund of the entire amount paid as contemplated under Section 18 of the RERA Act.

Point 2: Builder defaulted on reimbursement obligations of bank’s pre-EMI amount

In view of the builder having failed to reimburse all the pre-EMIs to the homebuyer as agreed under the pre-EMI document and the letter of undertaking, which resulted in the homebuyer having made payment to the financial institute where he had availed the loan, and on account of the builder’s failure to give possession on time as promised, which again resulted in the homebuyer having continued to pay pre-EMI till July 2024, and further if the homebuyer had not approached the Karnataka High Court, he would have to make the payment of pre-EMI to the complainant until possession was given to the homebuyer.

In the case being referred to here, the homebuyer has withdrawn on account of no possession being given, and the builder has failed to discharge the homebuyer from making payment of pre-EMI by closing the loan account standing in the name of the homebuyer with the financial institution as agreed by the builder.

The homebuyer is neither beneficiary of the property nor of the loan amount as both are retained by the builder.
Karnataka RERA

Zahir Tapia – Associate, ALMT Legal, says: "The homebuyer in this matter was successful as the developer failed to hand over possession to the homebuyer by the contractually agreed date of 31st March 2017. This clearly constituted a breach under Section 18(1) of the Real Estate (Regulation and Development) Act, 2016, which provides for refund with interest in case of delayed possession.

Further, the developer had acknowledged and accepted the homebuyer’s cancellation of the apartment booking through an email dated 23rd April 2017, following the homebuyer’s email dated 18th January 2017. This showed mutual agreement on withdrawal, validating the buyer’s entitlement to a refund. Moreover, under the Pre-EMI Scheme and Letter of Undertaking dated 26th May 2014, the developer was obligated to service the EMIs on the loan availed by the buyer on cancellation. However, upon cancellation, the developer failed to foreclose the loan or repay the pre-EMIs already paid by the buyer, despite their express contractual responsibility to do so.

In this regard, the Authority also observed that the buyer had received neither the property nor the benefit of the loan, both being retained by the developer. The financial burden unfairly fell on the buyer even after cancellation. The Authority also held that excuses such as rainfall, demonetisation, COVID-19, and shortage of materials were rejected as insufficient and routine construction risks, especially since COVID-19 post-dated the promised delivery date in 2017. Furthermore, the developer failed to produce any documentary evidence on project status, progress, or justification for delay, weakening its defence and reinforcing the complainant’s case.."

What are some key legal takeaways from this judgement

ET Wealth Online has asked various experts about what might be some key legal takeaways from this judgement. Here's what they said:

Whatsapp BannerAvikshit Moral, Partner, S&R Associates: There was substantial delay in handing over possession of the unit by the developer to the complainant which entitled him to exit from the project. The authority did not see merit in the reasons cited by the Respondent for such delay. It is this case the developer has been directed to refund the principal with interest thereon. But what makes this order interesting is the fact that the principal refund amount includes his self-contribution together with the amount paid by him as EMI to financial institution as per a private agreement executed between the complainant, respondent, and the financial institution. So, the principal refund amount seems to be much higher than the total cost of the unit.

Rohan Marathe – Senior Associate, ALMT Legal: This judgment affirms that developers remain liable to foreclose home loans and refund EMIs when a Pre-EMI scheme has been executed, especially after cancellation is accepted. The order also underscores that failure to deliver possession within the stipulated period entitles the buyer to a full refund with interest, even years after the agreed date. The judgment clarifies that Covid-19 cannot be cited as a defence for delays pre-dating the pandemic. The Authority has clarified that once a developer has accepted a buyer’s cancellation in writing, it cannot later evade liability by delaying refund or failing to close the loan account.
Continue Reading
( Originally published on Apr 17, 2025 )

READ MORE ON

(Catch all the Personal Finance News, Breaking News, Budget 2025 Events and Latest News Updates on The Economic Times.)

Subscribe to ET Prime and read the ET ePaper online.

NEXT READ

NEXT STORY
universo-virtual.com
buytrendz.net
thisforall.net
benchpressgains.com
qthzb.com
mindhunter9.com
dwjqp1.com
secure-signup.net
ahaayy.com
soxtry.com
tressesindia.com
puresybian.com
krpano-chs.com
cre8workshop.com
hdkino.org
peixun021.com
qz786.com
utahperformingartscenter.org
maw-pr.com
zaaksen.com
ypxsptbfd7.com
worldqrmconference.com
shangyuwh.com
eejssdfsdfdfjsd.com
playminecraftfreeonline.com
trekvietnamtour.com
your-business-articles.com
essaywritingservice10.com
hindusamaaj.com
joggingvideo.com
wandercoups.com
onlinenewsofindia.com
worldgraphic-team.com
bnsrz.com
wormblaster.net
tongchengchuyange0004.com
internetknowing.com
breachurch.com
peachesnginburlesque.com
dataarchitectoo.com
clientfunnelformula.com
30pps.com
cherylroll.com
ks2252.com
webmanicura.com
osostore.com
softsmob.com
sofietsshotel.com
facetorch.com
nylawyerreview.com
apapromotions.com
shareparelli.com
goeaglepointe.com
thegreenmanpubphuket.com
karotorossian.com
publicsensor.com
taiwandefence.com
epcsur.com
odskc.com
inzziln.info
leaiiln.info
cq-oa.com
dqtianshun.com
southstills.com
tvtv98.com
thewellington-hotel.com
bccaipiao.com
colectoresindustrialesgs.com
shenanddcg.com
capriartfilmfestival.com
replicabreitlingsale.com
thaiamarinnewtoncorner.com
gkmcww.com
mbnkbj.com
andrewbrennandesign.com
cod54.com
luobinzhang.com
bartoysdirect.com
taquerialoscompadresdc.com
aaoodln.info
amcckln.info
drvrnln.info
dwabmln.info
fcsjoln.info
hlonxln.info
kcmeiln.info
kplrrln.info
fatcatoons.com
91guoys.com
signupforfreehosting.com
faithfirst.net
zjyc28.com
tongchengjinyeyouyue0004.com
nhuan6.com
oldgardensflowers.com
lightupthefloor.com
bahamamamas-stjohns.com
ly2818.com
905onthebay.com
fonemenu.com
notanothermovie.com
ukrainehighclassescort.com
meincmagazine.com
av-5858.com
yallerdawg.com
donkeythemovie.com
corporatehospitalitygroup.com
boboyy88.com
miteinander-lernen.com
dannayconsulting.com
officialtomsshoesoutletstore.com
forsale-amoxil-amoxicillin.net
generictadalafil-canada.net
guitarlessonseastlondon.com
lesliesrestaurants.com
mattyno9.com
nri-homeloans.com
rtgvisas-qatar.com
salbutamolventolinonline.net
sportsinjuries.info
topsedu.xyz
xmxm7.com
x332.xyz
sportstrainingblog.com
autopartspares.com
readguy.net
soniasegreto.com
bobbygdavis.com
wedsna.com
rgkntk.com
bkkmarketplace.com
zxqcwx.com
breakupprogram.com
boxcardc.com
unblockyoutubeindonesia.com
fabulousbookmark.com
beat-the.com
guatemala-sailfishing-vacations-charters.com
magie-marketing.com
kingstonliteracy.com
guitaraffinity.com
eurelookinggoodapparel.com
howtolosecheekfat.net
marioncma.org
oliviadavismusic.com
shantelcampbellrealestate.com
shopleborn13.com
topindiafree.com
v-visitors.net
qazwsxedcokmijn.com
parabis.net
terriesandelin.com
luxuryhomme.com
studyexpanse.com
ronoom.com
djjky.com
053hh.com
originbluei.com
baucishotel.com
33kkn.com
intrinsiqresearch.com
mariaescort-kiev.com
mymaguk.com
sponsored4u.com
crimsonclass.com
bataillenavale.com
searchtile.com
ze-stribrnych-struh.com
zenithalhype.com
modalpkv.com
bouisset-lafforgue.com
useupload.com
37r.net
autoankauf-muenster.com
bantinbongda.net
bilgius.com
brabustermagazine.com
indigrow.org
miicrosofts.net
mysmiletravel.com
selinasims.com
spellcubesapp.com
usa-faction.com
snn01.com
hope-kelley.com
bancodeprofissionais.com
zjccp99.com
liturgycreator.com
weedsmj.com
majorelenco.com
colcollect.com
androidnews-jp.com
hypoallergenicdogsnames.com
dailyupdatez.com
foodphotographyreviews.com
cricutcom-setup.com
chprowebdesign.com
katyrealty-kanepa.com
tasramar.com
bilgipinari.org
four-am.com
indiarepublicday.com
inquick-enbooks.com
iracmpi.com
kakaschoenen.com
lsm99flash.com
nana1255.com
ngen-niagara.com
technwzs.com
virtualonlinecasino1345.com
wallpapertop.net
nova-click.com
abeautifulcrazylife.com
diggmobile.com
denochemexicana.com
eventhalfkg.com
medcon-taiwan.com
life-himawari.com
myriamshomes.com
nightmarevue.com
allstarsru.com
bestofthebuckeyestate.com
bestofthefirststate.com
bestwireless7.com
declarationintermittent.com
findhereall.com
jingyou888.com
lsm99deal.com
lsm99galaxy.com
moozatech.com
nuagh.com
patliyo.com
philomenamagikz.net
rckouba.net
saturnunipessoallda.com
tallahasseefrolics.com
thematurehardcore.net
totalenvironment-inthatquietearth.com
velislavakaymakanova.com
vermontenergetic.com
sizam-design.com
kakakpintar.com
begorgeouslady.com
1800birks4u.com
2wheelstogo.com
6strip4you.com
bigdata-world.net
emailandco.net
gacapal.com
jharpost.com
krishnaastro.com
lsm99credit.com
mascalzonicampani.com
sitemapxml.org
thecityslums.net
topagh.com
flairnetwebdesign.com
bangkaeair.com
beneventocoupon.com
noternet.org
oqtive.com
smilebrightrx.com
decollage-etiquette.com
1millionbestdownloads.com
7658.info
bidbass.com
devlopworldtech.com
digitalmarketingrajkot.com
fluginfo.net
naqlafshk.com
passion-decouverte.com
playsirius.com
spacceleratorintl.com
stikyballs.com
top10way.com
yokidsyogurt.com
zszyhl.com
16firthcrescent.com
abogadolaboralistamd.com
apk2wap.com
aromacremeria.com
banparacard.com
bosmanraws.com
businessproviderblog.com
caltonosa.com
calvaryrevivalchurch.org
chastenedsoulwithabrokenheart.com
cheminotsgardcevennes.com
cooksspot.com
cqxzpt.com
deesywig.com
deltacartoonmaps.com
despixelsetdeshommes.com
duocoracaobrasileiro.com
fareshopbd.com
goodpainspills.com
kobisitecdn.com
makaigoods.com
mgs1454.com
piccadillyresidences.com
radiolaondafresca.com
rubendorf.com
searchengineimprov.com
sellmyhrvahome.com
shugahouseessentials.com
sonihullquad.com
subtractkilos.com
valeriekelmansky.com
vipasdigitalmarketing.com
voolivrerj.com
zeelonggroup.com
1015southrockhill.com
10x10b.com
111-online-casinos.com
191cb.com
3665arpentunitd.com
aitesonics.com
bag-shokunin.com
brightotech.com
communication-digitale-services.com
covoakland.org
dariaprimapack.com
freefortniteaccountss.com
gatebizglobal.com
global1entertainmentnews.com
greatytene.com
hiroshiwakita.com
iktodaypk.com
jahatsakong.com
meadowbrookgolfgroup.com
newsbharati.net
platinumstudiosdesign.com
slotxogamesplay.com
strikestaruk.com
trucosdefortnite.com
ufabetrune.com
weddedtowhitmore.com
12940brycecanyonunitb.com
1311dietrichoaks.com
2monarchtraceunit303.com
601legendhill.com
850elaine.com
adieusolasomade.com
andora-ke.com
bestslotxogames.com
cannagomcallen.com
endlesslyhot.com
iestpjva.com
ouqprint.com
pwmaplefest.com
qtylmr.com
rb88betting.com
buscadogues.com
1007macfm.com
born-wild.com
growthinvests.com
promocode-casino.com
proyectogalgoargentina.com
wbthompson-art.com
whitemountainwheels.com
7thavehvl.com
developmethis.com
funkydogbowties.com
travelodgegrandjunction.com
gao-town.com
globalmarketsuite.com
blogshippo.com
hdbka.com
proboards67.com
outletonline-michaelkors.com
kalkis-research.com
thuthuatit.net
buckcash.com
hollistercanada.com
docterror.com
asadart.com
vmayke.org
erwincomputers.com
dirimart.org
okkii.com
loteriasdecehegin.com
mountanalog.com
healingtaobritain.com
ttxmonitor.com
bamthemes.com
nwordpress.com
11bolabonanza.com
avgo.top